UPDATE 8 - The first DIPLE units are leaving our headquarters
about 6 years ago
– Thu, Sep 03, 2020 at 12:45:01 AM
Dear Backers,
Here the monthly update about the progresses on DIPLE
We have some important news:
1. We will start shipping a first group of units in the next 2-3 days. We are packing them now. First, the early bird with standard stage, almost 200 pieces.
3. About the kits with Fine Stage, we are waiting some parts to test from one of our suppliers. Indeed, while we validated the representative samples of all the components some weeks ago, a couple of type of components coming out from the mass production process are out of tolerance. Therefore, we are working to solve these issues in the shortest time, refining and changing some minor details. We are confident to solve these problems in the next weeks and to start shipping the first group of DIPLE kits with fine stage before the end of September; we will communicate every important information about this issue.
4. DIPLE Lux: we will receive all the assembled PCB in the next few days. The containers for the circuit are under production now and they will be delivered to us in two weeks, so we should be ready to ship the first units before the end of this month, too.
Assembled PCB for DIPLE Lux
In addition:
We are very proud to inform that 2 independent professors at the University of Wisconsin and at the Cornell University (two top Universities in the World University Ranking) tested and selected the DIPLE kits (with standard stage, the only version available also for tests, rights now) for their remote courses of the next Fall. 😊
Thanks for your support in these extra-tough days and Stay Safe!
The SMO Team
Follow us on Instagram @diplemicro, Facebook @diplemicro, Youtube: https://bit.ly/2TBfhct
------------
This time we want also let you know about a couple of interesting projects (one very scientific, the other very portable, both features in common with DIPLE):
The Microcosm in Glass is a collection of 3D laser etched models of viruses, bacteria and cells.
The microscopic cracks inside the glass reflect light and turn these solid glass cubes into beautiful and educational decorative objects.
Choose from Covid-19, water bears, bacteriophages and many other interesting models.
With Magnetic Rotating Mechanism, it feels like the lid is hovering. This is the most effortless organizer for your Everyday Carry Objects.
Update 7
over 6 years ago
– Tue, Jul 28, 2020 at 01:00:02 AM
Dear Backers,
Here the new monthly update about the progresses on DIPLE
The work keeps moving, but with some obstacles. Nothing serious but it will take some more days to fix.
The shipment of DIPLE with standard stages will have some days of delay on the timing anticipated in the previous updates; the plan was to start shipping in the end of July/beginning of August. Now, we need about 2-3 weeks more. The reason of this delay is a problem with the manufacturing of the external parts of the boxes. As reported in other updates, we decided to make both the internal and external part of the box in plastic, instead of thick cardboard. So, the whole product is much more solid and long lasting than the one showed in the campaign. As you can see in the next video, the samples that we got from our supplier do not fit well. Therefore, we have asked for a change in the mold; it will take about 10 more days. We expect to be ready to ship the units with standard stages within the end of August. These issue will not affect the plan for the shipment of the units with fine stage, as it was already estimated within the end of September.
The other parts making up the product are ready. In the next pic you can see the first batch of DIPLE. Once the external part of the boxes will be ok, our partner in China will ship them to our headquarters; then, we will insert the components (objective lenses and some other components) made in Italy and we’ll be ready to ship the DIPLE units to you in few days.
Diple units with standard stage
Thanks for your support and Stay Safe!
The SMO Team
Follow us on Instagram @diplemicro, Facebook @diplemicro, YouTube: https://bit.ly/2TBfhct
Update 6
over 6 years ago
– Sat, Jul 04, 2020 at 12:43:22 AM
Dear Backers,
Here the sixth, monthly update about the progresses on DIPLE
We ordered all the parts that we need to assembly the DIPLE units during May and June, to our suppliers.
We have been informed of some delays for parts of the Fine Stage and parts made of transparent plexiglass. These problems are related to: 1. Excessive bending of Aluminum plates during the step of anodization; the manufacturer needed some days to optimize the process, now it seems to be solved. 2. The parts of transparent plastic (slide shifters) have a delayed delivery because there is shortage of transparent sheets in this period, because this material is extremely requested for making shields (for Covid19 related products).
Tiles for Diple Grey and Plates for Standard Stages
All the molds for injection molding should be completed within few weeks. According to the timing provided from our suppliers, we will be able to test the pieces coming from the molds for mass production in mid-July.
Pic of the molds, from our supplier
We sent the Backerkit survey some weeks ago; in June we ordered all the materials requested to also prepare the add-ons.
We plan to build and ship the first units starting from the end of July/beginning of August.
The first orders to ship will be the units with Standard Stage; these units have less components, and, in particular, do not have the parts for which we have been informed about the aforementioned delays. For the units with Fine Stage we think to start the shipments in late August/September. We can write this scheduling, following the information from our suppliers, and assuming normal lead time for the ordered components. In May we experienced a delay of 3 weeks for custom inspection on a DHL express shipment; this kind of delays is obviously out of our control.
We will share with you a more precise calendar once will have received all the components in our warehouse.
This week we have completed the lens manufacturing phase (we make the lenses in our headquarters in Italy). Now we have 1000 red objective lenses ready to ship. In the next 2 weeks we will receive other DIPLE red tiles and the tiles for the assembly of the Diple Grey and Black lenses. We have made thousands of lenses, now we have to mount them in the tiles.
1000 Diple Red objective lenses, ready to ship
Within the next week we should be ready to print also the instruction foils. This point can appear a detail, but it is not. We have improved the system during the last months (DIPLE is now much better than during the Kickstarter campaign), and the description of its components and how to manage them has changed. The instruction must be clear and short (otherwise no one read them, as I use to do…). Therefore, we’ll make some video tutorial, and we will probably improve the instruction in the next months, according to the feedback of the users. We will always share new versions of instructions on our website.
We are now working also on the file management for the invoicing and for preparation of the shipping labels. Our shipping provider has changed its file management system since our previous Kickstarter campaign of four years ago, so we must change the way to prepare these documents. Moreover, in addition to all the Covid19-related problems, we have been informed few weeks ago about the doubling of the shipping cost for small packages to the US, starting right from July of this year (as reported here). Of course, this does not imply any cost for you, but it forces us to further focus on leaning all our logistic tasks.
Thanks for your support and Stay Safe!
The SMO Team
Follow us on Instagram @diplemicro, Facebook @diplemicro, Youtube: https://bit.ly/2TBfhct
Update 5 - May 2020
over 6 years ago
– Fri, May 29, 2020 at 02:13:51 AM
Dear Backers,
Here is the fifth, monthly update about the progresses on DIPLE
On May 4th we re-opened the company, after the long lock-down.
The Covid-related hurdles were not over with the end of the lock-down: mechanical parts from foreign manufacturers that we needed to check and validate were stuck at the custom for 3 weeks as the priority was given to goods for the virus emergency. However, we got the box last week. But I want to make the story short and go directly to the point of highest interest: we plan to start the shipment of the first units before the end of July. About a couple of months of delay, as anticipated in previous updates. Those of you that work in manufacturing or in tech innovation can understand the amount of unexpected problems of the last few months. Extra problems, in addition to all the issues that can be found bringing a hardware product from prototype stage, to mass production.
The first units ready to ship will be likely those with DIPLE standard stages, that have a smaller number of components. From the end of August and September we plan to ship the other kits; we have actually some details to adjust, about mechanical tolerances; the fine-stage is made of 19 different pieces and we found some manufacturing issues in the pre-production batch on two of these parts. You can be sure that we will make our best to ship as soon as possible; any delay is a cost for us.
Said that, in the next few days we will send to all of you our survey via Backerkit. You will find there a showroom where you will be able to upgrade the ordered item with accessories or new parts. We need you to fill your shipping information there, too.
About the product, we are proud to have improved it significantly since the end of the Kickstarter campaign (thanks to your feedback and to our beta testers):
- The box is now made of ABS; the internal and the external part of the box are made of plastic. So, it is tougher and long-lasting.
- The second problem reported in the former review was solved too; the blocking elements that keep the tile in position can be now regulated, tightening or releasing a screw. We provide a little screwdriver in the box, for these little adjustments, too.
- The fine stage can be used also as a standard stage or used with non-standard glass slides. In the current, final design it is possible to remove two parts that keep a standard slide in position.
- We provide also a box with glass coverslips, for properly preparing your own experience.
The final, internal part of the box, objective lenses and accessories. Final design (except for colors) of the fine stage.
System with standard stage and Diple Grey. iPhone on blood cells
Moreover, we are preparing the instruction booklet and we have almost finished a manual with examples of experiences to share with you.
Update 4 - April 2020
over 6 years ago
– Fri, Apr 24, 2020 at 11:46:51 PM
Dear Backers,
Here the fourth, monthly update about the progresses on DIPLE
One month ago I mentioned that we suspended part of the works, due to the Covid-19 related lock-out. Unfortunately, our Country (Italy), has been severely affected, and the lock-down is still active. According to the current available information, we’ll be allowed to re-open on May,4.
This will lead to a delay. We will do our best to keep this delay as short as possible. The last part of development of a hardware product and its rump-up production are not easy steps even in normal conditions. For providing you backers with more details, we mention here some problems that we have faced in these weeks (obviously unexpected during the Kickstarter campiagn): 1. stop of our internal manufacturing of optics, due to lock-down; 2. some of our Italian suppliers of custom-made parts are on lock-down too, or have addressed their efforts toward the manufacturing of parts urgently needed by hospitals; 3. delays in the shipments of components (not all the couriers are working in Italy, and all of them have delays); 4. we canceled a travel in China for organizing part of the procurements (mentioned in the update of February; at that time it was only postponed), due to the travel limitations and quarantines; 5. we had to dedicate more time for managing urgent aspects directly, or indirectly, related to the health emergency, so limiting our time for the product development.
Nevertheless, there are good news 😊:
- We have ordered molds for injection molding for the mass production of many of the parts
- We have received and tested the pre-production batches of the metallic tiles of the objective lenses (from 2 different suppliers) and of the stages. We’ll order the mass production of these parts in the next few days.
Diple tiles, from pre-production batch
Aluminum plates for Fine and Standard stages, from pre-production batches.
- We have selected all the suppliers for the components of the systems (accessories included)
- We have decided to add a box with cover glasses for microscope (100pcs) within every DIPLE box. During the Kickstarter campaign we though to provide thin, transparent foils, in the place of coverslips; we have noted that their quality is not good enough for microscopy at the magnifying level of DIPLE. It is an important accessory in the use of the system, so we will add this component.
- We are preparing a manual with experiences for exploring the microscopic world using DIPLE and some examples of use. We plan to expand it in the future, also with feedback from DIPLE users who want to take part in it.
In conclusion, we can estimate a delay of about 8-10 weeks, that is approximately the duration of the Italian lock-down (March,8 – May,4), unexpected during the campaign. We plan to send you a survey for collecting your shipping information and for offering possible upgrades of your rewards before the end of May.
Thanks for your support and Stay Safe!